The Kwai Chung Hospital Phase 2 project involves redevelopment of a new campus offering comprehensive psychiatric in-patient, ambulatory, and community services. Itʼs the first Architectural Services Department's project in which MiMEP was implemented by the MEP subcontractor independently ofArchitectural Services Department's by a builder.
The team integrated a range of MiMEP modules—including combined MEP ceiling modules, trunking risers, pump sets, MCB boards etc.—exceeding contract requirements for added value.
Their strategy included Native BIM, mock-ups, off-site fabrication and precise on-site connections since 2019. Utilising Southaʼs ISO 9001 certified local fabrication yard significantly reduced cross-border logistics risks for this project, especially as most installation work took place during the COVID years.
Their approach focused on both on-site and off-site MiMEP planning, rigorous safety measures, and optimised installation sequencing. They also leverage innovative technologies like Openspace, Dalux, and QR code to enhance quality and progress monitoring.
The MiMEP approach improved sustainability, safety, cost efficiency, and project timelines.
Client
Employer
Architect
Main Contractor
Structural Engineer
Building Services Engineer
MEP Specialist Contractor
MiMEP Supplier
Highlights on Current Status
In-use
Project Current Status
Completed
No. of MiMEP Modules
1,216
CFA (m²)
132,300
MiMEP CFA (m²)
95,256
Superstructure Storeys
15
MiMEP Storeys
15
MiMEP Area to CFA in Typical floors (%)
72
Construction Commencement Date
Dec 2019
Date of Completion
Apr 2025
MiMEP Coverage (%)
80
| Module Type | Description | W (mm) | L (mm) | H (mm) | Weight (kg) | Qty |
|---|---|---|---|---|---|---|
| Pipe Riser | Chilled and hot water riser pipe with tee-off at AHU room | 2100 | 4500 | 750 | 1500 | 72 |
| Integrated AHU | Valve set for AHU and PAU | 2300 | 4500 | 1800 | 2500 | 128 |
| Pump Drop | Valve set for Water Pumps (AC) | 800 | 2500 | 500 | 500 | 64 |
| Pump Drop | Valve set for FS/SPR/ SFH/ Pumps | 500 | 1500 | 800 | 200 | 14 |
| Pump Drop (Large) |
Valve set for pumping system pump (Large) |
500 | 1500 | 800 | 200 | 46 |
| Trunking Riser | Trunking Riser in ELV room |
1500 | 3600 | 200 | 600 | 39 |
| Control Panel | Control Panel for ELV system in ELV room | 1000 | 1500 | 500 | 100 | 26 |
| Switchgear and MCB Board | Switchgear and MCB Board in EL Room | 2700 | 3700 | 1100 | 500 | 272 |
| Combined MEP module | Combined E & M services at the typical corridor | 1200 | 2440 | 1200 | 460 | 288 |
| Valve set | Valve set for pumping system with pump | 800 | 1700 | 200 | 600 | 42 |
| Trunking Riser | Trunking Riser in HAIT Room | 1500 | 3600 | 500 | 200 | 142 |
| FS Jockey Pump Set | FS Jockey Pump Set | 800 | 1700 | 1500 | 300 | 10 |
| Sprinkler Control Valve Set | Sprinkler Control Valve Set | 800 | 1300 | 2170 | 200 | 8 |
| Sprinkler Subsidiary Valve Set | Sprinkler Subsidiary Valve Set | 600 | 1400 | 400 | 200 | 76 |
| Heat Transfer Compact Unit | Heat Transfer Compact Unit | 2600 | 2100 | 2000 | 700 | 16 |
|
|
|
|
|
|
Total |
1216 |