West Kowloon Government Offices

11 Hoi Ting Road, Yau Ma Tei, Kowloon
Courtesy of FSE Engineering Group Limited

West Kowloon Government Offices (WKGO) comprise twin 15- and 17-storey towers respectively over a two-level basement, 98,000m² CFA housing seven departments plus student health and special assessment center, civil service dental clinic, and property / facility support.

 

Off-site prefabricated cooling tower and pipework modules (≤5m × 4m × 3.5m, <5t), factory assembled, QA tested and just-in-time craned, enabled 90% of placement, connection and testing in 11 days; the remaining ~10% was mainly cable pulling, wiring and terminations.

 

A federated BIM drove clash analysis, 4D sequencing, embedded quantities and procurement data, optimised temporary works, logistics and safe pedestrian / vehicular separation. RTS total station set-out, 3D scanning and VR validation improved alignment and field adjustments. Resulting in MEP works shortened by 3 months with fewer defects, reduced work at height, lower waste, noise, traffic disruption and embodied carbon, which set a benchmark digitally enabled, sustainable workplace.

Highlights on Current Status

In-use

Project Current Status

Completed

No. of MiMEP Modules

31

CFA (m²)

98,000

MiMEP CFA (m²)

475

Superstructure Storeys

37

MiMEP Storeys

2

MiMEP Area to CFA in Typical floors (%)

16

Construction Commencement Date

Jul 2015

Date of Completion

Aug 2018

MiMEP Coverage (%)

0.6

Construction Commencement

Jul 2015

Manufacture of MiMEP Modules

Sep 2017 - May 2018

Installation of MiMEP Modules

Sep 2017 - May 2018

Completion

Aug 2018

Module Type Description W (mm) L (mm) H (mm) Weight (kg) Qty

Cooling Tower System

Cooling tower modules consisting of prefabricated pipework, valves, energy meters, support for cooling tower, cable containments
and vibration isolators

4000

5000

3500

4800

22

Horizontal Ceiling
Modules

Ceiling modules consist of a main support frame for trunkings, cable tray, air ducts, chilled water pipes, fan coil units, etc.

2200

2900

500

160

9

 

 

 

 

 

Total

31

    The information contained in this page has been authorised being uploaded.

     

    Disclaimer

    The CIC does not warrant or guarantee the accuracy and suitability of the information contained in this page in any particular case. The CIC disclaims all liabilities for any loss or damage to any person arising from or as a consequence of the use of or reliance on any information contained in or omitted from this page.

Last Updated: 20.04.2026 16:49:51

About MiMEP

Multi-trade Integrated Mechanical, Electrical and Plumbing (MiMEP) is the integration of multi-trade building services components, into a single volumetric assembly of prefabricated modules, manufactured off-site in a workshop, then transported to the site for connection of modules to complete various trades of building services installations to minimise on-site works. MiMEP can integrate with structural element, architectural builders’ works and finishes (ABWF) to form an advanced assembly, such as false ceiling unit and plant room unit to enhance the productivity.

About MiMEP