West Kowloon Government Offices (WKGO) comprise twin 15- and 17-storey towers respectively over a two-level basement, 98,000m² CFA housing seven departments plus student health and special assessment center, civil service dental clinic, and property / facility support.
Off-site prefabricated cooling tower and pipework modules (≤5m × 4m × 3.5m, <5t), factory assembled, QA tested and just-in-time craned, enabled 90% of placement, connection and testing in 11 days; the remaining ~10% was mainly cable pulling, wiring and terminations.
A federated BIM drove clash analysis, 4D sequencing, embedded quantities and procurement data, optimised temporary works, logistics and safe pedestrian / vehicular separation. RTS total station set-out, 3D scanning and VR validation improved alignment and field adjustments. Resulting in MEP works shortened by 3 months with fewer defects, reduced work at height, lower waste, noise, traffic disruption and embodied carbon, which set a benchmark digitally enabled, sustainable workplace.
Main Contractor
Structural Engineer
Building Services Engineer
MEP Specialist Contractor
MiMEP Supplier
Highlights on Current Status
In-use
Project Current Status
Completed
No. of MiMEP Modules
31
CFA (m²)
98,000
MiMEP CFA (m²)
475
Superstructure Storeys
37
MiMEP Storeys
2
MiMEP Area to CFA in Typical floors (%)
16
Construction Commencement Date
Jul 2015
Date of Completion
Aug 2018
MiMEP Coverage (%)
0.6
| Module Type | Description | W (mm) | L (mm) | H (mm) | Weight (kg) | Qty |
|---|---|---|---|---|---|---|
|
Cooling Tower System |
Cooling tower modules consisting of prefabricated pipework, valves, energy meters, support for cooling tower, cable containments |
4000 |
5000 |
3500 |
4800 |
22 |
|
Horizontal Ceiling |
Ceiling modules consist of a main support frame for trunkings, cable tray, air ducts, chilled water pipes, fan coil units, etc. |
2200 |
2900 |
500 |
160 |
9 |
|
|
|
|
|
|
Total |
31 |
About MiMEP