Construction of Public Housing Development at Kwu Tung North Area 19 Phase 1A and Phase 1B

Kwu Tung North Area 19
Kwu Tung North Area 19 Phase 1

The project is located in Kwu Tung North Area 19 Phase 1A and Phase 1B. There are six 38-40 storey domestic blocks with 4,968 flats by MiC. 

Highlights on Current Status

Superstructure Works

Project Current Status

Under Construction

No. of MiC Modules

12,950

CFA (m²)

220,924

MiC CFA (m²)

135,727

Construction Cycle of Typical MiC Floor (@Day Cycle)

4

Total Storeys

38 - 40

MiC Storeys

Block 1: 40; Blocks 2 - 5: 39; Block 6: 38

Construction Commencement Date

Phase 1A: Q2 2022; Phase 1B: Q3 2023

Date of Completion

TBA

Structure

Concrete

Foundation Works (Phase 1A)

Q2 2022 - Q3 2023

Foundation Works (Phase 1B)

Q2 2023 - Q1 2024

Main Contract Commenced

Q3 2023

The information contained in this page has been authorised being uploaded.

 

Disclaimer

The CIC does not warrant or guarantee the accuracy and suitability of the information contained in this page in any particular case.  The CIC disclaims all liabilities for any loss or damage to any person arising from or as a consequence of the use of or reliance on any information contained in or omitted from this page

Last Updated: 24.05.2024 15:21:05

About MiMEP

Multi-trade Integrated Mechanical, Electrical and Plumbing (MiMEP) is the integration of multi-trade building services components, into a single volumetric assembly of prefabricated modules, manufactured off-site in a workshop, then transported to the site for connection of modules to complete various trades of building services installations to minimise on-site works. MiMEP can integrate with structural element, architectural builders’ works and finishes (ABWF) to form an advanced assembly, such as false ceiling unit and plant room unit to enhance the productivity.